Neodrill WSS – Wellhead Support System
- jostein38
- Jun 4
- 5 min read

Key features
High load capacity to withstand drive/drift-off loads
Wellhead fatigue protection
Highly efficient compared to alternative WLR (Well Load Relieve = Teathered BOP)
o Less equipment cost
o Less logistic cost (installation and retrieval of system)
The Neodrill WSS is literally “based” on the CAN technology, where the CAN provides a stable subsea foundation for the support elements that relieve the loads coming from the BOP.


In simple terms the WSS is a structureal element that is placed between the wellhead and the BOP. It consists of a (high capacity) mandrel, an adaptor plate, and a conventional connector in the axial direction (top to bottom) and a support frame in the lateral direction. Hydraulic jacks/tension struts warrant the installation and prevent tight manufacturing tolerances.
Wellhead Fatigue Mitigation
BOP loads are taken up by the WSS to a high degree and diverted into the CAN before they reach the wellhead system. This substantially reduces fatige damage of the wellhead system during the drilling phase. Once the drilling phase is completed the WSS can be taken off, making room for the SPS equipment (such as flow base, x-mas tree, etc.).
The degree of fatigue relieve depends on the relative stiffness between the well and the WSS system. This means …
The stiffer the WSS system, the lower fatigue damage inflicted into the wellhead
The more flexible the wellhead, the lower fatigue damage inflicted into the wellhead
The table below shows the improvement for three different scenarios. The dimension (diameter, wallthickness) of the conductor is the main contributor to wellhead stiffnes. One can see that the “more flexible” the conductor is, the higher the fatigue life factor for the wellhead system. This is of course a a relative measurement, as the absolute fatigue life of a 36x2” conductor is higher than that of a 30x1.5” conductor.
For cases where the conductor is not selected yet (new wells), one has the freedom to choose the appropriate conductor size. However, for existing wells (see below, P&A case) this behaviour is in fact good news as the WSS system can divert more than 90 % of the loads coming from the BOP.


Application Case (A) – Fatigue Protection for Production Wells with CAN/WSS
For wells being drilled by a CAN-ductor the implementation of the WSS is straight forward.
The CAN-ductor is installed by a CSV or AHTS vessel
The rig drills and cements the surface casing
A slim hole well program is enabled by the CAN-ductor, the 20” section may be dropped and replaced by the 13-3/8” section
The rig runs the WSS, which is connected to the CAN by ROV
The rig installes the BOP on top of the WSS and executes the drilling phase as per conventional drilling program
This phase is the main contributor of fatigue damage due to the high loads coming from the BOP
The WSS can prevent at least 80 % of the loads, which translates to fatigue life increase of a factor of 100 (or more), due to the non-linear (cubic) behavior of fatigue damage (e.g., 50 % reduction of load translates to a fatigue damage of 50%^3 = 12.5% fatigue damage)
Once the completion is installed, the BOP is removed, making room for SPS equipment
For cases where workover operations are required, or for cases where the P&A activities need to be carried out while the tree is still on place an extended version of the WSS can be supplied

Application Case (A) – Fatigue Protection for Existing Wells (P&A Activities)
The CAN/WSS combination may also be used for P&A activities of existing wells.
The process for this is shown below, and causes less cost for equipment and logistics compared to the teathered BOP method.
The x-mas tree is removed, and a guide frame is installed
This guide frame enables Neodrill to install a CAN over the existing well
Once the CAN is in place the process continues by installing the WSS system, connecting it the the wellhead and to the CAN
All operations up to this stage are done from a crane vessel, no rig time is required
With the WSS in place it is now safe to connect a modern BOP to the well, as most of the loads of said BOP are diverted via the WSS directly into the CAN
The remaining load going into the original wellhead is less than 10 % compared to a direct connection of the BOP to the original well
Once the P&A activities are completed the well is cut below seabed
This may be done by the rig, but can also be done by wire from a crane vessel by using the Terminator tool of BakerHughes
Neodrill cooperates with BakerHughes and has done several wellhead cutting operations in joint operations during CAN retrieval campaigns
The CAN and guide frame are recovered and may be used on the next well

Application Case (C) – Drive/Drift-Off Protection for Production Wells with CAN/WSS
For wells being drilled by a CAN-ductor the implementation of the WSS is straight forward.
The CAN-ductor is installed by a CSV or AHTS vessel
The rig drills and cements the surface casing
A slim hole well program is enabled by the CAN-ductor, the 20” section may be dropped and replaced by the 13-3/8” section
The rig runs the WSS, which is connected to the CAN by ROV
The rig installes the BOP on top of the WSS and executes the drilling phase as per conventional drilling program
This phase is the main contributor of fatigue damage due to the high loads coming from the BOP
The WSS can prevent at least 80 % of the loads, which translates to fatigue life increase of a factor of 100 (or more), due to the non-linear (cubic) behavior of fatigue damage (e.g., 50 % reduction of load translates to a fatigue damage of 50%^3 = 12.5% fatigue damage)
Once the completion is installed, the BOP is removed, making room for SPS equipment
For cases where workover operations are required, or for cases where the P&A activities need to be carried out while the tree is still on place an extended version of the WSS can be supplied

Summary
Key advantages for all presented cases
Substantially decreases fatigue damage for exploration and production wells, increased fatigue life (depending on wellhead stiffness) of a factor of 100 and far beyond
Enables safe and efficient P&A activities of existing wells with unknown remaining fatigue life
Allows utilization of high capacity wellhead connector systems without the need to deviate from established standard connectors on the wellhead system or the SPS equipment
Avoids cost and complex logistics to use the teathered BOP system
Lowers overall well cost by saving rig time for conductor installation
Moves a good amount of rig time to less costly crane vessel time
Please contact us at www.neodrill.com for further information, I’m sure we can contribute to your challenges.